Decision details

P/22/716/FUL - Land to the South of Felindre Road, Pencoed, CF35 5HU

Decision Maker: Development Control Committee

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decisions:

RESOLVED:                              That the above application be granted, subject to the Conditions contained in the report of the Corporate Director - Communities :-

 

Proposal:

 

Tactics facility building & external tactics equipment with access, landscaping, engineering and infrastructure works

 

Subject to Condition 1 of the report now reading as follows:-

 

1. The development shall be carried out in accordance with the following  approved plans and documents:

• Proposed Site Plan (ref. ZZ 00 90 100 rev. P12);

• Proposed Ground Floor Plan (ref. JFU-PDA-ZZ-00-DR-A-(05)200 rev. P05);

• Proposed First Floor Plan (ref. JFU-PDA-ZZ-01-DR-A-(05)201 rev. P06);

• Proposed Elevations 01 (ref. JFU-PDA-ZZ-ZZ-DR-A-(05)202 rev. P07);

• Proposed Elevations 02 (ref. JFU-PDA-ZZ-ZZ-DR-A-(05)203 rev. P07).

 

Reason: To avoid doubt and confusion as to the nature and extent of the

approved development.

 

Subject also to Condition 11 of the report being amended to read:

 

11. The acoustic barriers and bunds shall be erected at the locations and  heights as shown in Figure 8.2 of the noise impact assessment by MACH Group (document reference: JFU-MAC-ZZ-XX-RP-Y-1001_Noise Impact Assessment_P04) and as shown on the amended site plan entitled JFU_PDA_ZZ-00-DR_A_90100-Proposed Site Plan (including the additional new proposed barrier at the Bus Location shown in Figure 1.1 of the technical note JFU-MAC-ZZ-XX-RP-Y-1007_Acoustic Response to Pre-Committee Comments). The acoustic barriers and bunds shall have a minimum mass density of at least 12kg/m2 mass per unit area and be a solid construction, with no gaps between the floor and the acoustic screen, must be non-permeable, rot-proof and have no gaps within the acoustic barrier itself.  Prior to construction of the barriers/bunds, the design details shall be submitted to the Local Planning Authority for prior approval and shall be agreed in writing. The details shall include a location plan showing the position of the barriers, construction details and details confirming that the barrier/bunding has a minimum mass density of at least 12kg/m2. The design shall be implemented as agreed and the barrier shall be maintained in good condition and be retained in perpetuity. Should any part of the barrier become seriously damaged such that the effectiveness of its attenuation is reduced, it shall be repaired in good time with like-for-like materials, unless the Local Planning Authority gives written consent to any variation.

 

Reason: In the interest of protecting the amenity of neighbouring uses.

Publication date: 10/01/2024

Date of decision: 19/10/2023

Decided at meeting: 19/10/2023 - Development Control Committee

Accompanying Documents: